​The project provides for the construction of a new approximately 12,000 sf neighborhood/community center  (single story building) located in Gramercy Park.  The Center consists of a large multi-purpose room, classrooms, kitchen, offices and building support spaces.  Site amenities include a parking lot, landscaping and a mulch-surfaced walking trail.


Project Team:
Project Manager:
Stuart Patterson
561-233-0705
SPatterson@pbcgov.org


A/E Firm:
Architecture Green LLC
Construction Manager at Risk: Kaufman Lynn Construction, Inc.
________________________________________
Status:
Phase 1 - completed
Phase II  - under design 
Construction begins - Spring 2024
Construction completion - TBD